Same; recovery of capital expenditures for transmission facilities.

Checkout our iOS App for a better way to browser and research.

66-1242. Same; recovery of capital expenditures for transmission facilities.
Upon application, the commission shall provide for recovery of capital expenditures for construction or upgrade of any electric transmission line or appurtenances over a period of 15 years, unless: (a) The commission determines there is good cause to deny the application; or (b) recovery of capital expenditures for construction or upgrade of the transmission line or appurtenances is already provided for by tariffs and rates approved by the federal energy regulatory commission or its successors.

History: L. 2004, ch. 120, § 3; July 1.


Download our app to see the most-to-date content.