Reimbursement of Costs of Unnecessary Relocation; Conditions

Checkout our iOS App for a better way to browser and research.

Sec. 7. The department shall reimburse a utility for the costs of an unnecessary relocation of facilities if, after the completion of the relocation of the facilities:

(1) within two (2) years after the completion the department has not let a contract for the highway or bridge construction or improvement; or

(2) the department alters the department's plan of construction for the highway or bridge construction or improvement in a manner that would cause the utility to relocate the utility's facilities for the same highway or bridge construction or improvement project.

As added by P.L.63-1992, SEC.4.