Electricity Supplier's Petition to Commission for Recovery of Energy Delivery Costs Attributable to Distributed Generation Customers; Approval; Findings by Commission

Checkout our iOS App for a better way to browser and research.

Sec. 19. (a) To ensure that customers that produce distributed generation are properly charged for the costs of the electricity delivery system through which an electricity supplier:

(1) provides retail electric service to those customers; and

(2) procures excess distributed generation from those customers;

the electricity supplier may request approval by the commission of the recovery of energy delivery costs attributable to serving customers that produce distributed generation.

(b) The commission may approve a request for cost recovery submitted by an electricity supplier under subsection (a) if the commission finds that the request:

(1) is reasonable; and

(2) does not result in a double recovery of energy delivery costs from customers that produce distributed generation.

As added by P.L.264-2017, SEC.6.


Download our app to see the most-to-date content.