Sec. 21. (a) An application for a permit for substantial modification of a wireless support structure must include only the following:

(1) All information required by section 19 of this chapter.

(2) A construction plan that describes the proposed modifications to the wireless support structure and all equipment and network components, including antennas, transmitters, receivers, base stations, power supplies, cabling, and related equipment.

(3) If an applicable zoning ordinance specifies that a special exception, special use, contingent use, or conditional use must be approved for the proposed substantial modification of a wireless support structure in accordance with IC 36-7-4-918.2, evidence showing that the application complies with the criteria set forth in the ordinance with respect to the special exception, special use, contingent use, or conditional use.

(4) If the proposed substantial modification of a wireless support structure is not a permitted use under an applicable zoning ordinance, evidence showing that the application complies with the criteria for a variance of use from the terms of the zoning ordinance in accordance with IC 36-7-4-918.4.

A permit authority may not require an applicant to submit information about, and may not evaluate an applicant's business decisions with respect to, the applicant's designed service, customer demand, service quality, or desired signal strength to a particular location.

(b) An application that contains the information required under subsection (a) is considered complete.

(c) A permit authority shall review an application within ten (10) business days of its receipt to determine if the application is complete. If a permit authority determines that an application is not complete, the permit authority shall notify the applicant in writing of all defects in the application. If a permit authority does not notify an applicant in writing of all defects in the application, the application is considered complete.

(d) An applicant that receives a written notice under subsection (c) may cure the defects set forth in the notice and resubmit the corrected application to the permit authority within thirty (30) days of receiving the notice. If an applicant is unable to cure the defects within the thirty (30) day period, the applicant shall notify the permit authority of the additional time the applicant requires to cure the defects.

(e) Subject to subsection (f), not more than ninety (90) days after making an initial determination of completeness under subsection (c), a permit authority shall:

(1) review the application to determine if it complies with applicable laws and ordinances governing land use and zoning; and

(2) notify the applicant in writing whether the application is approved or denied.

(f) Notwithstanding the ninety (90) day period set forth in subsection (e), the following apply:

(1) If the applicant requested additional time under subsection (d) to cure defects in the application, the ninety (90) day period set forth in subsection (e) is extended for a corresponding amount of time.

(2) If the application for the proposed substantial modification of a wireless support structure requires a variance of use from the terms of an applicable zoning ordinance in accordance with IC 36-7-4-918.4, the permit authority may have not more than thirty (30) additional days to comply with subsection (e).

As added by P.L.145-2015, SEC.3.