Sec. 13. (a) This section applies to an eligible utility for which the commission has issued an order approving a petition under section 12(d) of this chapter.

(b) An eligible utility shall file a petition for a change in its adjustment amount:

(1) not more than thirty (30) days after the end of each twelve (12) month period following the date on which the eligible utility files a petition under section 12 of this chapter; and

(2) until the commission issues an order in the eligible utility's next general rate case proceeding after the commission approves a system integrity adjustment.

(c) An eligible utility shall serve the office of the utility consumer counselor a copy of the petition at the same time the petition is filed with the commission.

(d) The commission shall hold a hearing on the petition and issue its order not later than ninety (90) days after the petition is filed.

As added by P.L.104-2016, SEC.3.