Cost Recovery; Substitute Natural Gas Contracts

Checkout our iOS App for a better way to browser and research.

Sec. 42.1. (a) As used in this section, "substitute natural gas" means pipeline quality gas produced by a facility that uses a gasification process to convert coal into a gas capable of being used:

(1) by a utility to supply gas utility service to end use consumers in Indiana; or

(2) as a fuel used by a utility to produce electric power to supply electric utility service to end use consumers in Indiana.

(b) As used in this section, "customer choice program" means a program under which residential and commercial consumers located in the service area of a gas or electric utility may:

(1) purchase their supply from a provider other than the utility in the service area; and

(2) receive transportation service from the utility in the service area for the delivery of the supply purchased under subdivision (1) to the consumer's premises.

(c) Subject to IC 8-1-8.9 and notwithstanding any other law, if the commission approves a contract for the purchase of substitute natural gas, or electricity generated in connection with the production of substitute natural gas, by a utility, the commission shall allow the utility to recover the following costs on a timely basis throughout the term of the contract:

(1) All costs incurred in connection with and resulting from the utility's purchases under the contract, including the cost of the substitute natural gas and related costs for generation, transmission, transportation, and storage services.

(2) All costs the utility incurs in obtaining replacement gas if the seller fails to deliver substitute natural gas required to be delivered under the contract, including the price of the gas, and related transportation, storage, and hedging costs, to the extent those costs are not paid by the seller.

(3) Upon petition by the utility, any other costs the commission finds are reasonably necessary in association with the contract.

(d) Any costs recovered under subsection (c):

(1) are in addition to the recovery of other costs; and

(2) shall be made through an adjustment under section 42 of this chapter or another rate adjustment mechanism that allows for comparable timely cost recovery.

(e) If a customer choice program is implemented, expanded, or renewed for a utility during the term of a contract approved by order of the commission under subsection (c) that has the effect of reducing the utility's sales volumes, a condition of the authorization of that program must be the proportionate assignment of the gas or electric utility's substitute natural gas purchase obligation to the service providers in the customer choice program that meets the assignment requirements in the approved contract.

(f) Regardless of changes in market conditions or other circumstances, the commission may not take any action during the term of a contract approved under this section that adversely affects a utility's right to timely recover costs under this section or to otherwise fully recover such costs.

(g) With respect to utilities that are parties to a contract for the purchase of substitute natural gas approved by the commission under this section, the state covenants and agrees that as long as the contract is in effect the state will not limit, alter, or impair a utility's right to recover costs as provided in this section. Notwithstanding any other law, neither the commission nor any other state agency, political subdivision, or governmental unit may take any action that would have the effect of limiting, altering, or impairing a utility's right to recover costs as provided in this section.

As added by P.L.175-2007, SEC.9. Amended by P.L.52-2008, SEC.2.