Subdivision Control; Secondary Approval of Plat; Authority to Grant; Time; Prerequisites for Legal Effect of Plat

Checkout our iOS App for a better way to browser and research.

Sec. 710. (a) The plan commission may grant secondary approval of a plat under this section or may delegate to the plat committee or staff the authority to grant such secondary approvals.

(b) Secondary approval may be granted, after expiration of the time provided for appeal under section 708 of this chapter.

(c) No notice or hearing is required, and the provisions of this series concerning notice and hearing do not apply to secondary approvals.

(d) A plat of a subdivision may not be filed with the auditor, and the recorder may not record it, unless it has been granted secondary approval and signed and certified by the official designated in the subdivision control ordinance governing the area. The filing and recording of the plat is without legal effect unless approved by the commission, committee, or staff.

[Pre-Local Government Recodification Citations: 18-7-2-55; 18-7-4-710; 18-7-4-61; 18-7-5-47 part; 18-7-5-52.]

As added by Acts 1981, P.L.309, SEC.23. Amended by Acts 1981, P.L.310, SEC.39; Acts 1982, P.L.211, SEC.14; P.L.126-2011, SEC.21.