Dividing Cost of a Single Public Work Project Into Two or More Projects; Prohibition; Penalty

Checkout our iOS App for a better way to browser and research.

Sec. 19. (a) For purposes of this section, the cost of a public work project includes the cost of materials, labor, equipment rental, and all other expenses incidental to the performance of the project.

(b) The cost of a single public work project may not be divided into two (2) or more projects for the purpose of avoiding the requirement to solicit bids.

(c) A bidder or quoter or a person who is a party to a public work contract who knowingly violates this section commits a Class A infraction and may not be a party to or benefit from any contract under this chapter for two (2) years from the date of the conviction.

(d) Any board member or officer of a political subdivision or agency who knowingly violates this section commits a Class A infraction.

As added by P.L.216-1986, SEC.1.