Notice Upon Receipt of Application

Checkout our iOS App for a better way to browser and research.

Sec. 8. (a) Upon receiving a complete application for a construction permit, the state department shall notify the applicant not later than the next business day of all the following:

(1) The assigned project number.

(2) Instructions on submitting any required documentation.

(3) The contact information for the person performing the plan review, including any person, entity, or local health department that is delegated a plan review as provided in section 12 of this chapter.

(b) Not later than thirty (30) business days after the date a complete application is received by the state department, the state department shall:

(1) conduct a plan review; and

(2) notify the applicant that:

(A) the plans and specifications have been approved; or

(B) a construction permit will not be issued until the applicant submits corrections to the plans or specifications.

If the plans and specifications are approved, the state department shall issue the construction permit to the applicant not later than the thirty-first business day after the application is received.

As added by P.L.49-2016, SEC.1.


Download our app to see the most-to-date content.