Effect of Commencement of Construction or Operation of Equipment or Facility

Checkout our iOS App for a better way to browser and research.

Sec. 14. Except for applicants proceeding under section 11(a) of this chapter, an applicant may not proceed under any of the options described in section 11(b) of this chapter if construction or operation of the equipment or facility described in the permit application has already begun, unless construction or operation before obtaining the permit is authorized by a board rule or state statute.

[Pre-1996 Recodification Citation: 13-7-10.1-8(d).]

As added by P.L.1-1996, SEC.5. Amended by P.L.184-2002, SEC.7.