DEEP INJECTION WELLS — CONSTRUCTION — MODIFICATION — USE — PERMIT REQUIRED.

Checkout our iOS App for a better way to browser and research.

42-3903. DEEP INJECTION WELLS — CONSTRUCTION — MODIFICATION — USE — PERMIT REQUIRED. No new deep injection well shall be constructed after the effective date of this act unless a permit therefor has been issued by the director of the department of water resources. No deep injection well existing on the effective date of this act shall be modified after the effective date of this act unless a permit therefor has been issued by the director. No deep injection well existing on the effective date of this act shall continue to be used and maintained after January 1, 1974, unless a permit therefor has been issued by the director.

History:

[42-3903, added 1971, ch. 301, sec. 3, p. 1235; am. 1974, ch. 20, sec. 38, p. 533; am. 2011, ch. 110, sec. 3, p. 288.]