Reviews under this chapter shall be conducted in accordance with the following procedures:
(1) Notices of intent. — At least 30 days but not more than 180 days prior to submitting an application for review under this chapter, applicants shall submit to the Bureau a notice of intent in such form as may be determined by the Board to cover the scope and nature of the project. An application may be submitted less than 30 days from submitting the notice of intent only with the written approval of the Board. A notice of intent expires and is rendered invalid if no subsequent application for review is submitted to the Board within 180 days following the date on which the notice of intent is submitted.
(2) Applications for review. — Application forms will be developed by the Board and may vary according to the nature of the application.
(3) Deadlines and time limitations. — Upon receipt of an application under this chapter, the Bureau shall have a maximum of 15 business days to notify the applicant as to whether the application is considered complete. If complete, written notification in accordance with paragraph (4) of this section will be provided. If incomplete, the applicant will be notified in writing of such determination and will be advised of what additional information is required to make the application complete. When the additional information is received, the Bureau again has a maximum of 15 business days to determine whether the application is complete. The same steps shall be taken as with the initial submission each time that additional information is required.
Except as provided below, the review of an application shall take no longer than 90 days from the date of notification as covered under paragraph (4) of this section. If a public hearing is requested under paragraph (6) of this section, the maximum review period will be extended to 120 days from the date of notification. Within 30 days from the date of notification (60 days if a public hearing is requested), the Board may extend the maximum review period up to 180 days from the date of notification. Such extensions shall be invoked only as necessary to allow the development of appropriate review criteria or other guidance when these are lacking or to facilitate the simultaneous review of similar applications. The maximum review period can also be extended as mutually agreed to in writing by the Board and the applicant.
In the case of a project required to remedy an emergency situation which threatens the safety of patients or the ability of the health facility to remain in operation, an abbreviated application shall be submitted in such format as the Board prescribes. As quickly as possible, but within 72 hours after receipt, the Board shall render a decision as to whether or not the project shall be treated as an emergency and whether or not the application shall be approved. The Chair or Vice Chair of the Board shall be authorized to render such decision and shall have discretion as to the decision making process.
(4) Agency review; notification. — Within 5 working days of determining that an application under this chapter is complete, the Bureau shall provide written notification of the beginning of a review. Such notification shall be sent directly to all health care facilities in the State and to others who request direct notification. A notice shall also appear in a newspaper of general circulation which shall serve as written notification to the general public. The date of notification is the date on which such notice appears in the newspaper. The notification shall identify the applicant, indicate the nature of the application, specify the period during which a public hearing in the course of the review as covered in paragraph (6) of this section may be requested, and indicate the manner in which notice will be provided of the time and place of any hearing so requested.
(5) Findings. — Upon completion of a review under this chapter, and within the time frames outlined in paragraph (3) of this section, the Bureau shall notify in writing the applicant and anyone else upon request as to the Board's decision, including the basis on which the decision was made. Decisions can be conditional, but the conditions must be related to the specific project in question.
(6) Public hearing in the course of review. — Within 10 days after the date of notification as described in paragraph (4) of this section, a public hearing in the course of review may be requested in writing by any person. The Board shall provide for a public hearing if requested and shall provide notification of the time and place for such hearing in a newspaper of general circulation. The public hearing shall be held not less than 14 days after such notice appears in the newspaper. Fees shall not be imposed for such hearings. An opportunity must be provided for any person to present testimony.
(7) Administrative reconsideration — Procedure for Board. — Any person may, for a good cause shown, request in writing a public hearing for purposes of reconsideration of a Board decision rendered under paragraph (5) of this section. The Board may not impose fees for such a hearing. For purposes of this paragraph, a request for a public hearing shall be deemed by the Board to have shown good cause if it:
a. Presents newly discovered, significant, relevant information not previously available or considered by the Board; and
b. Demonstrates that there have been significant changes in factors or circumstances relied upon by the Board in reaching its decision; or
c. Demonstrates that the Board has materially failed to follow its adopted procedures in reaching its decision.
A request for such a hearing must be received within 10 days of the decision. The hearing shall commence within 45 days of the request.
Notice of such public hearing shall be sent, not less than 15 days prior to the date of the hearing, to the person requesting the hearing and to the applicant, and shall be sent to others upon request. Following completion of the hearing, the Board shall, within 45 days, issue its written decision which shall set forth the findings of fact and conclusion of law upon which its decision is based.
(8) Appeal — Applicant. — A decision of the Board following review of an application pursuant to paragraph (5) of this section, an administrative reconsideration pursuant to paragraph (7) of this section, or the denial of a request for extension of a Certificate of Public Review pursuant to § 9307 of this title, may be appealed within 30 days to the Superior Court. Such appeal shall be on the record.
(9) Access by public. — The general public shall be provided access to all applications reviewed under this chapter and to all other written materials pertinent to any review of an application.
(10) Filing fees. — Within 5 working days of determining that an application under this chapter is complete, the Bureau shall notify the applicant of any filing fee due.
Filing fees shall be determined from the following table:
Filing | |
Capital Expenditures | Fee |
Less than $500,000 | $100 |
$500,000 to $999,999 | $750 |
$1,000,000 to $4,999,999 | $3,000 |
$5,000,000 to $9,999,999 | $7,500 |
$10,000,000 and over | $10,000 |
Filing fees shall be due 30 days after the date of notification of the beginning of review as covered under paragraph (4) of this section. This due date may be extended up to 10 additional days at the discretion of the Bureau. Applications for which filing fees have not been paid within this time frame shall be considered to be withdrawn. All filing fees shall be deposited in the General Fund.