Inventory of land uses overlying aquifers.

Checkout our iOS App for a better way to browser and research.

Not later than three months after approval of the Commissioner of Energy and Environmental Protection of mapping of aquifers at level B, each municipal aquifer protection agency authorized pursuant to section 22a-354o shall inventory land uses overlying the mapped zone of contribution and recharge areas of such aquifers in accordance with guidelines established by the commissioner pursuant to section 22a-354f. Such inventory shall be completed not more than one year after authorization of the agency.

(P.A. 88-324, S. 5; P.A. 89-305, S. 27, 32; P.A. 11-80, S. 1.)

History: P.A. 89-305 required inventory to be completed within a year of agency authorization and made technical changes; pursuant to P.A. 11-80, “Commissioner of Environmental Protection” was changed editorially by the Revisors to “Commissioner of Energy and Environmental Protection”, effective July 1, 2011.

Cited. 215 C. 616.