(1) The department may use a design-build contract for a transportation project if the design work for such project must be performed before a potential bidder can develop a price or cost proposal for such project and if the chief engineer of the engineering, design, and construction division determines that using a design-build contract is appropriate. The chief engineer shall consider the following factors in making a determination pursuant to this subsection (1):

  1. The extent to which the transportation project requirements are adequately defined;

  2. The time constraints for completing the transportation project;

  3. The capability and experience of potential design-build firms;

  4. The suitability of the transportation project to a design-build contract; and(e) The capability of the department to manage the design-build contract.

(2) The department may use a design-build contract regardless of the estimated minimum or maximum cost of a transportation project.

Source: L. 99: Entire part added, p. 258, § 1, effective April 9.