(1) The rates and charges schedule for services provided by a program created under section 40-5-107 may allow:
A return on any investment made under section 40-5-107 by an electric public utilityat the electric public utility's weighted average cost of capital, including the most recent rate of return on equity, approved by the commission, including by allowing a utility to earn a rate of return on rebates provided to customers through a transportation electrification program;
Rate recovery mechanisms that allow earlier, as determined by the commission, recovery of costs, including the use of rate adjustment clauses; and
Performance-based incentive returns or similar investment incentives.
(2) By May 15, 2020, an electric public utility shall submit to the commission a proposal for a specific rate or rates for electricity supplied to commercial and industrial facilities used to charge electric vehicles that encourage vehicle charging and that support the operation of the electric grid.
Source: L. 2019: Entire section added, (SB 19-077), ch. 383, p. 3434, § 3, effective May 31.
Cross references: For the legislative declaration in SB 19-077, see section 1 of chapter 383, Session Laws of Colorado 2019.