Action commenced within six months.

Checkout our iOS App for a better way to browser and research.

Every person, firm, or corporation filing a statement as provided in section 38-24-104 and claiming a lien under this article shall commence suit thereon in the district court of the county in which the statement is filed not later than six months after the date of such filing, and the lien shall remain in force until the final determination of such suit. Costs shall be divided according to the justice of the case.

Source: L. 29: p. 437, § 5. CSA: C. 101, § 55. CRS 53: § 86-5-5. C.R.S. 1963: § 86-55.