Section 9516.

Checkout our iOS App for a better way to browser and research.

(a) (1) Before adopting, or increasing, a fee described in this part, or adopting or changing the terms and conditions of access subject to this part, the local publicly owned electric utility shall hold at least one open and public meeting as part of a regularly scheduled meeting, at which time oral or written presentations relating to the fee or term or condition of access may be made.

(2) At least 14 days before the meeting described in paragraph (1), the local publicly owned electric utility shall mail notice of the time and place of the meeting, including a general explanation of the matter to be considered, and a statement that the data required by paragraph (3) is available, to a person or entity who files a written request with the local publicly owned electric utility for mailed notice of the meeting.

(3) At least 10 days before the meeting described in paragraph (1), the local publicly owned electric utility shall make available to the public data indicating the cost, or estimated cost, to make utility poles and support structures available for use by a communications service provider, if adopting or increasing a fee, and shall make available data and rationale for adopting or changing the terms and conditions of access, if adopting or changing the terms and conditions of access.

(b) (1) An action by a local publicly owned electric utility to adopt, or increase, a fee described in this part, or adopt or change the terms and conditions of access subject to this part, shall be taken solely by an ordinance or resolution adopted, or by a contract approved, by the governing body of the local publicly owned electric utility. The governing body of the local publicly owned electric utility shall not delegate the authority to adopt or increase the fee or term or condition of access to another entity or board or an official or employee of the board. This subdivision does not restrict a city council’s existing authority over a governing body appointed by the city council. The governing body of the local publicly owned electric utility shall ensure that the customers of the local publicly owned electric utility and the customers of the communications service provider are not subsidized by the rates, terms, and conditions proposed for access pursuant to this part.

(2) The governing body of the local publicly owned electric utility shall approve the ordinance or resolution or contract to adopt or increase the fee, or adopt or change the terms and conditions of access subject to this part, at a subsequent open and public meeting as part of a regularly scheduled meeting, no earlier than 30 days after the initial public meeting described in subdivision (a).

(3) An action adopting a fee or increasing a fee, or adopting or changing the terms and conditions of access subject to this part, pursuant to this section shall be effective no sooner than 60 days following the final action on the adoption of the fee or fee increase or adoption or change in the terms and conditions of access.

(c) This section does not apply to a contract extension agreed to by all of the parties to the contract, if the terms, conditions, or rates described in the contract are not changed.

(Added by Stats. 2011, Ch. 580, Sec. 2. (AB 1027) Effective January 1, 2012.)


Download our app to see the most-to-date content.