Section 8414.

Checkout our iOS App for a better way to browser and research.

A claimant other than a direct contractor may not enforce a lien unless the claimant records a claim of lien within the following times:

(a) After the claimant ceases to provide work.

(b) Before the earlier of the following times:

(1) Ninety days after completion of the work of improvement.

(2) Thirty days after the owner records a notice of completion or cessation.

(Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)