Section 2780.1.

Checkout our iOS App for a better way to browser and research.

(a) It is the intent of the Legislature that the commission consider the legal, administrative, and operational costs that an electric microutility faces if it is named as a respondent in a hearing generally applicable to electrical corporations. The limited resources of a microutility are disproportionately strained by the cost of response.

(b) Further, it is the intent of the Legislature that the commission consider the costs described in subdivision (a) before naming an electric microutility as a respondent in a hearing generally applicable to electrical corporations.

(Added by Stats. 2004, Ch. 639, Sec. 1. Effective January 1, 2005.)