The approval of the notice by the commission shall be based upon findings pursuant to Section 25514. The notice shall not be approved unless the commission finds at least two alternative site and related facility proposals considered in the commission’s final report as acceptable. If the commission does not find at least two sites and related facilities acceptable, additional sites and related facilities may be proposed by the applicant which shall be considered in the same manner as those proposed in the original notice.
If the commission finds that a good faith effort has been made by the person submitting the notice to find an acceptable alternative site and related facility and that there is only one acceptable site and related facility among those submitted, the commission may approve the notice based on the one site and related facility. If a notice is approved based on one site and related facility, the commission may require a new notice to be filed to identify acceptable alternative sites and related facilities for the one site and related facility approved unless suitable alternative sites and related facilities have been approved by the commission in previous notice of intention proceedings.
If the commission finds that additional electric generating capacity is needed to accommodate the electric power demand forecast pursuant to subdivision (e) of Section 25305 and, after the commission finds that a good faith effort was made by the person submitting the notice to propose an acceptable site and related facility, it fails to find any proposed site and related facility to be acceptable, the commission shall designate, at the request of and at the expense of the person submitting the notice, a feasible site and related facility for providing the needed electric generating capacity.
(Amended by Stats. 1984, Ch. 1184, Sec. 11.)