After conclusion of the hearings held pursuant to Section 25513 and no later than 300 days after the filing of the notice, a final report shall be prepared and distributed. The final report shall include, but not be limited to, all of the following:
(a) The findings and conclusions of the commission regarding the conformity of alternative sites and related facilities designated in the notice or considered in the notice of intention proceeding with both of the following:
(1) The 12-year forecast of statewide and service area electric power demands adopted pursuant to subdivision (e) of Section 25305, except as provided in Section 25514.5.
(2) Applicable local, regional, state, and federal standards, ordinances, and laws, including any long-range land use plans or guidelines adopted by the state or by any local or regional planning agency, which would be applicable but for the exclusive authority of the commission to certify sites and related facilities; and the standards adopted by the commission pursuant to Section 25216.3.
(b) Any findings and comments submitted by the California Coastal Commission pursuant to Section 25507 and subdivision (d) of Section 30413.
(c) Any findings and comments submitted by the San Francisco Bay Conservation and Development Commission pursuant to Section 25507 of this code and subdivision (d) of Section 66645 of the Government Code.
(d) The commission’s findings on the acceptability and relative merit of each alternative siting proposal designated in the notice or presented at the hearings and reviewed by the commission. The specific findings of relative merit shall be made pursuant to Sections 25502 to 25516, inclusive. In its findings on any alternative siting proposal, the commission may specify modification in the design, construction, location, or other conditions which will meet the standards, policies, and guidelines established by the commission.
(e) Findings and conclusions with respect to the safety and reliability of the facility or facilities at each of the sites designated in the notice, as determined by the commission pursuant to Section 25511, and any conditions, modifications, or criteria proposed for any site and related facility proposal resulting from the findings and conclusions.
(f) Findings and conclusions as to whether increased property taxes due to the construction of the project are sufficient to support needed local improvements and public services required to serve the project.
(Amended by Stats. 2001, 1st Ex. Sess., Ch. 12, Sec. 4. Effective May 22, 2001.)