Section 25244.21.

Checkout our iOS App for a better way to browser and research.

(a) Every generator shall retain the original of the current review and plan and report, shall maintain a copy of the current review and plan and report at each site, or, for a multisite review and plan or report, at a central location, and upon request, shall make it available to any authorized representative of the department or the unified program agency conducting an inspection pursuant to Section 25185. If a generator fails, within five days, to make available to the inspector the review and plan or report, the department, the unified program agency, or any authorized representative of the department, or of the unified program agency, conducting an inspection pursuant to Section 25185, shall, if appropriate, impose a civil penalty pursuant to Section 25187, in an amount not to exceed one thousand dollars ($1,000) for each day the violation of this article continues, notwithstanding Section 25189.2.

(b) If a generator fails to respond to a request for a copy of its review and plan or report made by the department or a unified program agency pursuant to subdivision (a) of Section 25244.18, or by a local agency pursuant to subdivision (e) of Section 25244.18, within 30 days from the date of the request, the department or unified program agency shall, if appropriate, assess a civil penalty pursuant to Section 25187, in an amount not to exceed one thousand dollars ($1,000) for each day the violation of this article continues, notwithstanding Section 25189.2.

(c) (1) A person may request the department to certify that a generator is in compliance with this article by having the department certify that the generator has properly completed the review and plan and report required pursuant to Sections 25244.19 and 25244.20. The department shall respond within 60 days to a request for certification. Upon receiving a request for certification, the department shall request from the generator, who is the subject of the request, a copy of the generator’s review and plan and report, pursuant to subdivision (a) of Section 25244.18, if the department does not have these documents. The department shall forward a copy of the review and plan and report to the person requesting certification, within 10 days from the date that the department receives the request for certification or receives the review and plan and report, whichever is later. The department shall protect trade secrets in accordance with Section 25244.23 in a review and plan or report, requested to be released pursuant to this subdivision.

(2) This subdivision does not prohibit any person from directly requesting from a generator a copy of the review and plan or report. Solely for the purposes of responding to a request pursuant to this subdivision, the department shall deem the review and plan or report to be a public record subject to Section 25152.5, and shall act in compliance with that section.

(Amended by Stats. 2012, Ch. 39, Sec. 55. (SB 1018) Effective June 27, 2012.)