Section 2456.

Checkout our iOS App for a better way to browser and research.

An allocation for construction costs, including preconstruction costs if not already allocated, shall be made to a local agency only if it furnishes evidence satisfactory to the department that all necessary orders of the Public Utilities Commission have been executed, that sufficient local funds will be made available as the work of the project progresses, that all necessary agreements with affected railroad or railroads have been executed that, if required, all environmental impact reports have been prepared and approvals obtained, and that all other matters prerequisite to the award of the construction contract can be accomplished within two years after the allocation. Local funds shall be deemed available to the amount of any general obligation bonds authorized but unsold if it is determined that those bonds may be issued and sold by the local agency at any time.

(Amended by Stats. 2005, Ch. 298, Sec. 1. Effective January 1, 2006.)


Download our app to see the most-to-date content.