The notice of claim of lien shall contain all of the following information:

(a) The name and address of the lien claimant.

(b) The name and address of the lien debtor.

(c) The location of the property to which the equipment was returned.

(d) A statement that the payment of reasonable or agreed charges is more than 90 days overdue.

(e) The amount of the reasonable or agreed charges that are overdue.

(f) A statement, signed under penalty of perjury, that includes all of the following:

(1) That the lien claimant sent to the lien debtor the notice required pursuant to subdivision (a) of Section 22906.

(2) That more than 10 days have elapsed since the notice was received by the lien debtor.

(3) That the lien debtor has not complied with the requirements of subdivision (a) of Section 22906.

(g) A statement that the lien claimant has an equipment repurchase lien pursuant to Section 22906.