The preparation and certification of a master environmental impact report, if prepared and certified consistent with this division, may allow for the limited review of subsequent projects that were described in the master environmental impact report as being within the scope of the report, in accordance with the following requirements:
(a) The lead agency for a subsequent project shall be the lead agency or any responsible agency identified in the master environmental impact report.
(b) The lead agency shall prepare an initial study on any proposed subsequent project. This initial study shall analyze whether the subsequent project may cause any significant effect on the environment that was not examined in the master environmental impact report and whether the subsequent project was described in the master environmental impact report as being within the scope of the report.
(c) If the lead agency, based on the initial study, determines that a proposed subsequent project will have no additional significant effect on the environment, as defined in subdivision (d) of Section 21158, that was not identified in the master environmental impact report and that no new or additional mitigation measures or alternatives may be required, the lead agency shall make a written finding based upon the information contained in the initial study that the subsequent project is within the scope of the project covered by the master environmental impact report. No new environmental document nor findings pursuant to Section 21081 shall be required by this division. Prior to approving or carrying out the proposed subsequent project, the lead agency shall provide notice of this fact pursuant to Section 21092 and incorporate all feasible mitigation measures or feasible alternatives set forth in the master environmental impact report which are appropriate to the project. Whenever a lead agency approves or determines to carry out any subsequent project pursuant to this section, it shall file a notice pursuant to Section 21108 or 21152.
(d) Where a lead agency cannot make the findings required in subdivision (c), the lead agency shall prepare, pursuant to Section 21157.7, either a mitigated negative declaration or environmental impact report.
(Amended by Stats. 1994, Ch. 1294, Sec. 13. Effective October 1, 1994. Note: October 1, 1994, is the date that Ch. 1294 became law without the Governor's signature.)