Funding restrictions.

Checkout our iOS App for a better way to browser and research.

§ 3430.1005 Funding restrictions.

(a) Facility costs. Funds made available under the Sun Grant Program shall not be used for the construction of a new building or facility or the acquisition, expansion, remodeling, or alteration of an existing building or facility (including site grading and improvement, and architect fees).

(b) Indirect cost provisions for regional competitive research, extension, and education grant programs. Funds provided by NIFA to the Centers and Subcenter for the regional competitive grants program under § 3430.1004(a)(1) may not be used for the indirect costs of awarding the competitive grants. However, up to 4 percent of the total funds provided by NIFA to the Centers and the Subcenter under § 3430.1004 for the Sun Grant Program may be budgeted for administrative costs incurred in awarding the competitive grants.

(c) Indirect cost provisions for research, extension, and education activities conducted at the Centers and Subcenter. Subject to § 3430.54, indirect costs are allowable for the funds provided by NIFA to the Centers and the Subcenter for the research, extension, and education programs under § 3430.1004(a)(2).

(d) Required allocations. Each Center and Subcenter must fund subgrants in a proportion that is a minimum 30 percent for conducting multi-institutional and multistate research, extension, and education programs on technology development; and a minimum 30 percent for conducting integrated multi-institutional and multistate research, extension, and education programs on technology implementation. Each Sun Grant Center must clearly demonstrate a common procedure for ensuring the required allocations are met, and for maintaining documentation of these required percentages for audit purposes.

[75 FR 70580, Nov. 18, 2010, as amended at 81 FR 6418, Feb. 8, 2016]


Download our app to see the most-to-date content.