Application for approval.

Checkout our iOS App for a better way to browser and research.

§ 3300.43 Application for approval.

An application by an officer of the organization shall be submitted to the Administrator for each facility for which approval is sought. Copies of the Form, Application for Approval as a U.S. ATP Testing Laboratory, may be obtained by a request to the ATP manager. The following information must be supplied in the application:

(a) A statement that the organization is incorporated or chartered under the laws of, and that it has its principal office in, the United States, including the address and telephone number of the principal office.

(b) The address and telephone number of the testing laboratory, and name and title of person in charge of the laboratory.

(c) A summary of the experience at the facility which would indicate a capability to conduct tests of mechanical refrigerating appliances according to subpart D of this rule.

(d) A general description of the laboratory, including drawings on letter size (812 × 11 inches) paper to show the floor plan and cross-section of the test chamber, basic dimensions, location of heat exchangers and instruments, and any other pertinent information.

(e) A statement that the ATP manager or other representative of the Administrator may, before a decision is made concerning the application, observe a test at the laboratory of a mechanical refrigerating appliance for a Class “C” mechanically refrigerated container or trailer, with Class “C” as defined in ATP, Annex 1, paragraph 3.

(f) A statement that the laboratory will maintain records of basic data developed in each test conducted under this rule, such records to be available for review by the ATP manager or other representative of the Administrator, upon request. The record for each test shall be maintained for a period of three years.

(g) A statement that the organization will advise the ATP manager as soon as practicable of its intent to conduct a test under this rule and that it will, as soon as possible, advise when a firm test has been set so that the ATP manager or other representative of the Administrator may observe the test.

(h) A statement that the organization will send to the ATP manager a copy of each test report for an appliance tested at the laboratory according to this rule, within 30 days after completion of the test.

(i) A statement that, should any significant change occur in the facility with respect to structure or test equipment as a result of redesign or other cause during the period of approval, the organization will so advise the ATP manager within 30 days after such change.

(j) Any other pertinent information.


Download our app to see the most-to-date content.