Introduction.

Checkout our iOS App for a better way to browser and research.

§ 1724.1 Introduction.

(a) The policies, procedures and requirements in this part implement certain provisions of the standard form of loan documents between the Rural Utilities Service (RUS) and its electric borrowers.

(b) All borrowers, regardless of the source of financing, shall comply with RUS' requirements with respect to design, construction standards, and the use of RUS accepted material on their electric systems.

(c) Borrowers are required to use RUS contract forms only if the facilities are financed by RUS. Borrowers have three options:

(1) Submit the actual contract used for review and approval;

(2) Submit a certification that the required contract was used for the electric project or;

(3) Submit a certification that the contract was not used but the essential and identical provisions specifically listed in the certification were used in the contract for constructing the electric facilities.

[63 FR 35314, June 29, 1998, as amended at 84 FR 32617, July 9, 2019]