Exclusion from the project management oversight program.

Checkout our iOS App for a better way to browser and research.

§ 633.19 Exclusion from the project management oversight program.

The Administrator may, in compelling circumstances, determine that a project meeting the criteria of § 633.5(e)(1) is not a major capital project because project management oversight under this part will not benefit the Federal government or the recipient. Typically, this means a project that:

(a) Involves a recipient whose past record indicates the appropriateness of excluding the project from project management oversight under this part; and

(b) Involves such a greater level of financial risk to the recipient than to the Federal government that project management oversight under this part is made less necessary to secure the recipient's diligence.


Download our app to see the most-to-date content.