As prescribed in 632.908(a), the contracting officer may insert a clause substantially the same as follows:
(a) General. The Government shall pay the contractor as full compensation for all work required, performed and accepted under this contract, inclusive of all costs and expenses, the firm fixed-price stated in Section B of this contract.
[Use paragraph (b) only if partial payments apply. Otherwise, paragraph (a) above assumes the contractor will be paid in full amount upon completion of all contractural requirements.]
(b) Payment Schedule. Payments will be made in accordance with the following partial payment schedule:
Partial payment No. | Specific deliverable | Delivery date | Payment amount |
---|---|---|---|
1 | |||
2 | |||
3 |
[Continue as necessary]
(c) Invoice Submission. Invoices shall be submitted in an original and [contracting officer insert appropriate number of copies] to the office identified in Block 10 of the SF-26, Block 23 of the SF-33, or Block 18b of the SF-1449. To constitute a proper invoice, the invoice must include all items per FAR 52.232-25, “Prompt Payment”.
(d) Contractor Remittance Address. Payment shall be made to the contractor's address as specified on the cover page of this contract, unless a separate remittance address is specified below:
(End of clause)
[59 FR 66771, Dec. 28, 1994, as amended at 64 FR 43633, Aug. 11, 1999]