Final Inspection and Tests.

Checkout our iOS App for a better way to browser and research.

552.246-72 Final Inspection and Tests.

As prescribed in 546.312, insert the following clause:

Final Inspection and Tests (SEP 1999)

The Contractor shall give written notice to the Contracting Officer at least 10 calendar days before the date the work will be completed and ready for final inspection and tests. Final inspection and tests will begin within 10 calendar days after the date specified in the Contractor's notice unless the Contracting Officer determines that the work is not ready for final inspection and so informs the Contractor.

(End of clause)


Download our app to see the most-to-date content.