Use and possession prior to completion.

Checkout our iOS App for a better way to browser and research.

36.511 Use and possession prior to completion.

The contracting officer shall insert the clause at 52.236-11, Use and Possession Prior to Completion, in solicitations and contracts when a fixed-price construction contract is contemplated and the contract award amount is expected to exceed the simplified acquisition threshold. This clause may be inserted in solicitations and contracts when the contract amount is expected to be at or below the simplified acquisition threshold.

[48 FR 42356, Sept. 19, 1983, as amended at 60 FR 34759, July 3, 1995]