Making payments.

Checkout our iOS App for a better way to browser and research.

232.906 Making payments.

(a)

(i) Generally, the contracting officer shall insert the standard due date of 14 days for interim payments on cost-reimbursement contracts for services in the clause at FAR 52.232-25, Prompt Payment, when using the clause with its Alternate I.

(ii) The restrictions of FAR 32.906 prohibiting early payment do not apply to invoice payments made to small business concerns. However, contractors shall not be entitled to interest penalties if the Government fails to make early payment.

[70 FR 75413, Dec. 20, 2005, as amended at 76 FR 23506, Apr. 27, 2011]


Download our app to see the most-to-date content.