As prescribed in 1819.7302(b), insert the following clause:
The Contractor shall perform a minimum of one-half of the research and/or analytical effort (total contract price less profit) conducted under this contract. Any deviation from this requirement must be approved in advance and in writing by the Contracting Officer. Since the selection of R&D contractors is substantially based on the best scientific and technological sources, it is important that the Contractor not subcontract technical or scientific work without the Contracting Officer's advance approval.
(End of clause)
[71 FR 61688, Oct. 19, 2006]