When considering the use of a quality, performance, or schedule incentive, the following guidance applies:
(1) A positive incentive is generally not appropriate unless -
(i) Performance above the target (or minimum, if there are no negative incentives) level is of significant value to the Government;
(ii) The value of the higher level of performance is worth the additional cost/fee;
(iii) The attainment of the higher level of performance is clearly within the control of the contractor; and
(iv) An upper limit is identified, beyond which no further incentive is earned.
(2) A negative incentive is generally not appropriate unless -
(i) A target level of performance can be established, which the contractor can reasonably be expected to reach with a diligent effort, but a lower level of performance is also minimally acceptable;
(ii) The value of the negative incentive is commensurate with the lower level of performance and any additional administrative costs; and
(iii) Factors likely to prevent attainment of the target level of performance are clearly within the control of the contractor.
(3) When a negative incentive is used, the contract must indicate a level below which performance is not acceptable.
[63 FR 12997, Mar. 17, 1998, as amended at 69 FR 21764, Apr. 22, 2004]