§ 101-26.501-5 Procurement time schedules.

(a) Requisitions covering vehicle types included in Federal standard Nos. 122, 292, 307, 794, Federal specification Nos. KKK-T-2107, 2108, 2109, 2110, 2111, and Federal specification No. KKK-B-1579 will be procured either under a standardized buying program, as described in § 101-26.501-2, or a consolidated purchase program, as described in § 101-26.501-3, unless a statement is included justifying the need for delivery other than the delivery times indicated in this section. Requisitions containing a statement of justification will be handled on an emergency basis in accordance with § 101-26.501-5(b).

(b) Emergency requirements. Emergency requirements will receive special handling only when the requisitions are accompanied by adequate justification for individual purchase action. Every effort will be made to meet the delivery date specified in the requisition.

(c) Delivery time. Delivery times for motor vehicle requirements will range widely depending on method of purchase.

(1) Existing contracts. Delivery times for motor vehicle requirements submitted and placed against existing in-place contracts (family buy option, requirements contract or Federal Supply Schedule contract) will range from 60 to 150 days from date of purchase order.

(2) Volume consolidated procurements. Delivery times for motor vehicle requirements submitted for volume consolidated purchases will range from 210 to 330 days after solicitation consolidation date. Included in delivery time estimates are 90 to 105 days required for soliciting and receiving offers, 30 to 60 days for evaluation and award of contracts, 90 to 180 days from date of award for delivery of vehicles to destination (dealer or consignee, as applicable).

(3) For buses, ambulances, and other special duty vehicles which can not be procured under the standardized buying programs or consolidated purchase programs described in §§ 101-26.501-2 and 101-26.501-3, 240 to 270 days from date of award are usually required to effect delivery. However, special purpose vehicles with unique characteristics, such as certain types of firetrucks, may require longer delivery. In such instances, every effort will be made by GSA to facilitate deliveries and keep the requisitioning agencies informed of any unauthorized delay.

[57 FR 47778, Oct. 20, 1992]