§ 585.1014 When will BOEM suspend an Alternate Use RUE?

(a) BOEM may suspend an Alternate Use RUE if:

(1) Necessary to comply with judicial decrees;

(2) Continued activities pursuant to the Alternate Use RUE pose an imminent threat of serious or irreparable harm or damage to natural resources; life (including human and wildlife); property; the marine, coastal, or human environment; or sites, structures, or objects of historical or archaeological significance;

(3) The suspension is necessary for reasons of National security or defense; or

(4) We have suspended or temporarily prohibited operation of the existing OCS facility that is subject to the Alternate Use RUE, and have determined that continued activities under the Alternate Use RUE are unsafe or cause undue interference with the operation of the original OCS Lands Act approved activity.

(b) A suspension will extend the term of your Alternate Use RUE grant for the period of the suspension.