Who is responsible for the completion and maintenance of a conservation practice if the permit expires or is canceled before the completion of the conservation practice?

Checkout our iOS App for a better way to browser and research.

§ 166.315 Who is responsible for the completion and maintenance of a conservation practice if the permit expires or is canceled before the completion of the conservation practice?

Prior to undertaking a conservation practice, the BIA, landowner, and permittee will negotiate who will complete and maintain a conservation practice if the permit expires or is canceled before the conservation practice is completed. That conservation practice agreement will be reflected in the conservation plan and permit.


Download our app to see the most-to-date content.