The agreement must be promptly executed, in accordance with the following conditions:
(a) Prohibition of excess subsidy. The PHA may not enter the Agreement with the owner until the subsidy layering review is completed (see § 983.55).
(b) Environmental approval. The PHA may not enter the Agreement with the owner until the environmental review is completed and the PHA has received the environmental approval (see § 983.58).
(c) Prohibition on construction or rehabilitation. The PHA shall not enter into the Agreement with the owner if construction or rehabilitation has commenced after proposal submission.
[70 FR 59913, Oct. 13, 2005, as amended at 79 FR 36167, June 25, 2014]