§ 12.1 Applicability.

(a) Except as otherwise provided in this part or ordered by the Commission or its authorized representative, the provisions of this part apply to:

(1) Any project licensed under Part I of the Federal Power Act;

(2) Any unlicensed constructed project for which the Commission has determined that an application for license must be filed under Part I of the Act; and

(3) Any project exempted from licensing under Part I of the Federal Power Act, pursuant to subparts J or K of part 4 of this chapter, to the extent that the Commission has conditioned the exemption on compliance with any particular provisions of this part.

(b) The provisions of this part apply to a project that uses a Government dam only with respect to those project works, lands, and waters specifically licensed by the Commission.