(a) Modification procedure. If, prior to or after final disbursement of funds to a project from all funding sources, in order to remedy noncompliance or receive additional subsidy, there is or will be a change in the project that would change the score that the project application received in the AHP funding round in which it was originally scored and approved, had the changed facts been operative at that time, a Bank shall approve in writing a request for a modification to the terms of the approved application, provided that:
(1) The Bank first requests that the project sponsor or owner make a reasonable effort to cure any noncompliance within a reasonable period of time, and the noncompliance could not be cured within a reasonable period of time;
(2) The project, incorporating any such changes, would meet the eligibility requirements of this part;
(3) The application, as reflective of such changes, continues to score high enough to have been approved in the AHP funding round in which the application was originally scored and approved by the Bank, which is as high as the lowest ranking alternate approved for funding by the Bank if the Bank has a written policy to approve alternates for funding; and
(4) There is good cause for the modification, which may not be solely remediation of noncompliance, and the analysis and justification for the modification, including why a cure of noncompliance was not successful or attempted, are documented by the Bank in writing.
(b) AHP subsidy increases; no delegation -
(1) AHP subsidy increases. A Bank's board of directors may, in its discretion, approve or disapprove requests for modifications involving an increase in AHP subsidy in accordance with the requirements of paragraph (a) of this section.
(2) No delegation. The authority to approve or disapprove requests for modifications involving an increase in AHP subsidy shall not be delegated by the Bank's board of directors to Bank officers or other Bank employees.